MIVAN Shuttering 7 days Slab Cycle Complete Step by Step Procedure on site 🔰Best video to understand in Detail Watch Full video on YouTube channel DND Construction 🔰DAY 1 Activity : Grid line and thesi work Activity : vertical steel reinforcement work for Column, shear wall and nonstructural wals 🔰DAY 2 and 3 - Erection of MIVAN wall panels and deck panels work with all chajja's and elevations 🔰DAY 4 - Complete all beam and Slab Reinforcement work of slab with covering 🔰DAY 5 - Complete all slab electrical conduiting work with all MEP services if needed 🔰DAY 6 - Complete all grid line checking and Supporting of slab in all respect 🔰DAY 7 - Checking work Complete in all respective departments ( RCC consultant, architect, quality department, safety department and MEP) - finally do casting of MIVAN slab and repeat procedure for next slab #mivanformwork #mivanshuttering #mivan #slabcycles #slabconstruction #7daysslab https://www.instagram.com/p/CEvzS2dlnbE/?igshid=26u6bvn6wr00