Three factories, one delivery date: the marble-top problem
The hardest part of a restaurant furniture package is rarely the furniture. It is the calendar.
For a restaurant chain fit-out we supplied booth sofas, dining chairs and wood-frame tables with natural marble tops — 2 x 40HQ in total. Sounds simple until you map the production reality: upholstery came from a seating workshop, wood frames from a table factory, and the marble tops were fabricated separately by a stone specialist, then fitted to the frames.
Three specialist producers, three different production rhythms, one loading date. If the marble runs late, the finished tables don't exist yet — and the container either waits (storage, risk) or sails without them (a restaurant with no tables).
Our job as the sourcing agent was to sequence it: lock specifications early, schedule the stone fabrication against the frame production, and converge everything on a single consolidation and loading window. All inspected before shipment by our own team, with photo and video records.
One timeline, not three. That is what a multi-factory package actually requires.