Task Name Duration Predecessors ES EF LS LF SLACK
Task Name Duration Predecessors ES EF LS LF SLACK
Task Name Duration Predecessors ES EF LS LF SLACK for $5 Only (Instant Download)
Sample Answer Given Below
The project will be completed on 8th January, 2016The project will take a year and 6 days to complete. Based on the TABLE 1, the Critical path is 2,3,5,8,9,11,12,13,15,16,17 (activities with 0 slack)
Based on Table 1: The activity that has the greatest amount of slack is…