Slow Progress in Sunkoshi Marine Diversion Multipurpose Project Dam Construction
Only 7% physical progress achieved SINDHULI, Feb 26: The construction of the dam of the Sunkoshi Marin Diversion Multipurpose Project (SMDMP) is progressing at a sluggish pace. Although 42 percent of the project’s construction period has elapsed, the work progress is less than 10 percent. The construction company has struggled to advance the work, blaming the damage caused by floods in…