Transformation
As the land transforms, so does the confidence and hope the children have for their school and their own lives.
Day one, surveying the original piece of land over-looking the school where the boarding house will be situated.
A land scattered with trees. For every tree we had to remove, we will plant another 6-10.
The land is on a reasonable gradient which posed our largest challenge in the first month of pre-construction land preparations.
After 3 weeks of negotiations we managed to secure a grader from a near-by town that had just completed work on another project here in Mlali. Our options were to secure this grader at a slightly higher price or wait indefinitely for the only grader in Mlali to be repaired. Operators from the towns charge higher prices but there were no signs that the spare parts would be arriving anytime within the near future to allow us to use the Mlali grader.
The land is flattened within one day's work. Half way through the day it became apparent that levelling the land was not an option. Next step, confirm with the builders that they can construct the boarding house on this gradient.
Laying the markings for the foundation.
From a distance, the markings resemble our beautiful plan. The front of the boarding house over-looks the school and the savannah which will turn from red to green once the rains arrive.
The boys begin digging the foundation of the internal wing, destined to be home to 80 girls.
From dawn to dusk and through the long hot days in the African sun, they dug these foundations.
As the boys work hard to dig the trenches, the head builder follows not far behind with his team, laying cement in the freshly dug foundations.
The builder accounts for the gradient by terracing the land.
From day one, it took us almost 2 months to navigate our way through budgets, contracts, securing materials, labourers and equipment to arrive at this exciting new stage of construction. We began making the bricks a few days in advance to ensure they were strong enough and the walls started going up - a big step and achievement for all involved.
And the walls kept growing! The walls of the foundation for this wing will support four levels of flooring to account for the gradient.
The team works from the lowest point on the land where the walls are to be 10 bricks high, up to the highest point where the walls will be 3-4 bricks high.
While half the team continues building the walls of the foundation for the main section of the girls' wing, cement goes down in a new room attached to the side of the girls' wing.
The walls of the new room start going up.
Spaces have been left for steel reinforcements.
The steel reinforcement has arrived and all hands are on deck to install the steel rods and continue constructing the walls around them.
The head builder's main adviser and business partner, an essential man for getting the job done secures the wooden framework so concrete can be poured to keep the steel rods firmly in place.
The concrete is poured.
The concrete is setting for the most part of the new room. To the right, the walls of the foundation are extended. Faith, 12 poses for a photo on her daily visit to the boarding house.
The walls of the new room to the right grow to similar heights as those of the wing.
Two little visitors come to check on the progress of their new home to be, Julianna, 10 and Bahati, 11.
The concrete has set and the walls have gone up. This is the highest point of the foundation.
The external walls for the foundation of the girls' wing are almost complete.
The team move their focus to the three interior walls that will set the levels for the flooring.
In the meantime, the foundation of the side room needs to be filled with soil and compacted. Large stones will then be carefully placed to create a level platform, sand and water will be poured over them before the cement can go down to create the floor of the boarding house.
Work starts as the sun is coming up and finishes as the sun goes down most days.
The team makes progress on the three interior walls of the girls' wing.
Soil is placed in the four sections to create the four levels, soon to be the ground floor of this section of the home that will carry so many dreams and memories.
Each brick that goes into construction is made by hand on site, watered for 3-4 days to make sure they are strong enough for construction.
There were some nervous moments once the rains started as our truck tried to climb the steep, slippery terrain with 2 tonnes of materials in the back.
One week was spent building the water tank that proved essential to the construction process. We experienced many difficulties and tried many methods of getting the water from the source, 200 metres down the hill up to the tank. Water was a constant pressure and hindrance for progress.
The foundation for the boys' wing is much shallower as it is situated on the highest point of the land.
Each day the walls climb higher, grow longer, turn corners and the foundation of the boarding house begins to form as a physical structure, no longer only a reality in the heart and minds of all who have dreamt and invested in this ambitious project. This is no small project, destined to house 160 children, we are building a significant structure and we expect it to take another 6 months minimum before we have the boarding house almost ready for its new little inhabitants who will bring it to life.
The Human Transformation
While many of the students of the Queen Elizabeth Academy do have parents, there are a significant number who don't. The Queen Elizabeth Academy provides these students with a community, an identity, a support network and an education. This school is their hope and their joy. The boarding house will ensure the school can continue to provide this network of support to these students.
The increased income from the boarding house will allow the school to be on a more certain financial footing and this means the school can continue feeding all of their students during the months when food is in short supply.
Recently the water line was finished and there is now fresh water available at the school almost every day. Having water available is essential for the construction process but it also means that the students do not have to carry water to school each day. This is not too big a deal for the older children but it is nice to see the little ones do not have to carry their water containers. Again, as the school has a more secure income, costs such as maintenance on the waterline is a new possibility.
The Queen Elizabeth Academy is a place where children can be children and can explore the world of play between their classes. With the completed boarding house, we will be inviting another 160 children into this environment of exploration, safety and learning.
With school comes new uniforms, new knowledge and new confidence and each student wears their uniform with so much pride. The school is committed to providing all students with the support they need to arrive at school ready to learn, pencil and exercise book in hand. The founder of the Queen Elizabeth Academy personally helps students and their families to meet the costs of uniforms, new shoes, socks, books, pencils and much more. We will be able to meet these needs more efficiently as the school increases its financial sustainability.
Faith carries enormous pride in her school. When you meet her, she is quick to tell you that their school use to be in a room in the village where motorbikes use to drive past noisily interrupting lessons. Now Faith and the other 150 students have 4 classrooms, with another under construction, a soon to be fish pond, a boarding house in progress and acres of land that will be used to grow fresh food. Having all this in place for them speaks volumes in terms of how much we value each child and their education.
Thank you for helping us get this far and please come with us as we continue on this journey of transformation. stayclassy.org/kellyQEA









