28th July 2015 - It’s finished!
Well, nearly... We went through Practical Completion today, which is a walk-through of the house with the builder to check for anything not completed and that all is as per the contract. We found only minor issues that will be fixed tomorrow and as our last payment has been made, we are allowed the keys on Thursday hopefully!
There are some good tips here on what to look for on the walk-through: http://www.anewhouse.com.au/2012/01/practical-completion-inspection-12-hints/
We are still waiting for a part to install the solar hot water properly, and then we will make an appointment for a council-certified inspector to award us an occupation certificate (that is our understanding anyway, it is not crystal clear!)