Transmission Line Works to Clear Over 9,000 Trees Under Tanahu Hydropower Project
Damauli: A total of 9,127 trees will be removed for the construction of a transmission line under the Tanahu Hydropower Project. With the acquisition of user rights over 92.7 hectares of forest land in Tanahun and Chitwan districts for the construction of the Damauli–Bharatpur 220 kV transmission line under Package–3 of the project, permission has now been granted to clear the trees and…