Gantt Chart Reflection
Take the decision to study in a different country is always challenging and more if you don’t have an accurate plan. That was my case when I decided to move to Canada and make a Post Degree. I had a lot of problems with my visa and I came 2 weeks late to classes. After been in Canada for 3 months I have not only improved my english but also my skills by attending classes every week day to Centennial College. However to this you need to have a plan. At the beginning of the course I made a Gantt chart and the following words are my reflection.
How accurate was my planning?
Well I wasn't that bad as I thought it will be. I took my time to check every class in my Gantt chart and I have a little bit of everything. What I mean with a little bit of everything ? I have classes that were really well planed and also classes that were a complete chaos. Some of them, the problem was that I didn't have a specific course outline which made very difficult to plan something accurate. On the other hand I had a very specific course outline but my calculates about the time that I needed to complete every single task was wrong.
This is an approximate chart representing how accurate my plan was in each course.
Production tools 1
This was the only course that I planed totally right. Probably because I’m a developer or because the course outline was really straightforward. I did every assignment on time and following the structure in the Gantt chart. As well made the Gantt chart was easy because all assignments were similar and due to every week.
Emerging tools
The schedule for this course was simple. Basically a few tumblr posts and a final project. The only problem that I had to follow the schedule on the Gantt chart was the final project. Is difficult to make a plan for something that you don't know exactly the due dates. Also the outline for the final project wasn't very specific at all.
Digital Industry
The plan for this course was very similar to the Emerging tools. Very easy to made and also to follow. The challenging part was the final project. No due date in the outline so was difficult to plan something more accurate for this course.
Experience Design
I planed this course very good in terms of which assignment was required to do first. Each assignment required the finalization of the previous one. On the Gantt is well represented the connection between those assignments but the time required to finish them wasn't accurate at all. Additionally the final project wasn't represented as good as it could be.
Writing for Int. Media
Writing for Interactive Media and Experience Design share the same structure. Both courses have an structure that requires the finalization of each task before start a new one. That structure is well represented in my Gantt chart as well as the connection between all assignments and the final project.
Interactive Narrative 1
No Gantt chart at all because at that time I didn't have an outline for that class. In a real situation the best practice is to update the Gantt chart as soon as you get the information.
Skills for Collaborative Work
My plan for this course was the most inaccurate. Half of the tumblr assignments were made out of the plan. The interview with the leader is something that I had a lot of troubles and the Gantt chart could represent that task in a better way. Lack of emphasis in the time required not only to get the interview but also to do it.
Video and Sound
The schedule for this course was also very inaccurate. The personal video plan is based to hand a task every week however all assignments were handed the same day. Also was difficult to made a plan for the viral video presentation without a due date.
In conclusion if I need to make another Gantt chart I’ll take a few considerations before start doing it.
- Have all the due dates for every single task
- If a task depends of more than one person, talk with all the people involve with that task before.
- Take time to think outside the box for extra tasks that could be part of the Gantt chart.
- Update the Gantt chart as soon as any of the initial tasks planed change.
- If there’s no existing schedule for a specific tasks make one as accurate as possible.
In my opinion have a realistic Gantt chart is what really important. Doesn’t matter if you need to change that chart 5 times during your project to make it realistic because probably you’ll do changes to a Gantt chart no matter if it’s the best Gantt chart ever made. Follow a inaccurate plan if going to produce bad results. Hence updates are key to make the project keep on track during it’s execution.