GCQ update: Level 6 pour 1 is now complete and we have started lifting frames and tables up ready to form up level 7, & all perimeter scaffold on level 7 and level 6 pour 2 is complete and ready to provide access and fall protection. Formwork stripping to level 2 started last week and will provide access for the window contractor to start installing subsills this week. The subsills on ground floor are nearly complete and we will be in a position to install glass soon! 📸: @cobildconstruction . . . . . . #alpha14propertygroup #alpha14 #cobild #rfcorval #gcq #gippscromwellquarter #collingwood (at Collingwood, Victoria, Australia) https://www.instagram.com/p/CG1Nz6NFMfl/?igshid=f7e7agcp4wu0