Drainage Information to submit to council for approval:
Drainage Information to submit to council for approval:
Requirements:
I) Information required on the plan
i) Overall catchment area
ii) Location of internal drainage, pipe size material and grade
iii) Pit details, showing dimension, surface
iv) Location of storm water outlet
v) Details of all internal connections that are connected up to the OSD system before leaving site
II) Design parameters from a city council in Melbourne
Residential Development:
- Design storm period of 5 ARI
- Rainfall intensity based upon Australian Runoff 1987
- Coefficient runoff: pervious area 0.2, impervious area 0.8
Commercial Development
- Design storm period of 10 ARI
- Rainfall intensity same as for residential development
- Coefficient runoff: pervious area 0.1, impervious area 0.9
II) Prior to construction, the developer is to:
- Obtain approvals from relevant authorities
- Undertake all surveys
- Dial before you dig, and ensure all service information is present
- Present professional drafts